Job costing and books for contractors, remodelers and trades.

Averan Advisors keeps the books, closes the month and plans cash for businesses that sell jobs: remodels, roofs, decks, painting, plumbing and electrical work. Each section below explains one part of contractor bookkeeping, with a worked example in numbers.

Every dollar belongs to a job.

A contractor's sales and costs come one job at a time. Materials and crew hours make up most of the cost, so the books record each against its job. A job's margin is its sales less its own costs. The owner's overhead, such as the office, vehicles and insurance, sits outside the jobs.

Worked examples that name a brand use that brand's 2026 Franchise Disclosure Document (FDD), the document a franchisor gives a buyer before a sale. Other examples use round figures to show the method.

What materials and crews cost

Five remodel and trade brands in Averan's franchise library publish cost of goods as a share of sales.

BrandAverage salesCost of goodsEBITDA margin
Archadeck Outdoor Living$1,673,60759.8%2.2%
CertaPro Painters$2,102,01554.1%9.3%
Storm Guard$2,415,39552.0%12.7%
Bath Tune-Up$338,26851.0%Not reported
Garage Force$422,99830.0%Not reported

EBITDA is profit before interest, taxes, depreciation and amortization.

Worked example: Archadeck Outdoor Living

Archadeck reports average sales of $1,673,607, with cost of goods at 59.8% and wages at 20.0%. That is $1,000,817 of materials and subcontract cost and $334,721 of wages. Archadeck reports earnings before interest, depreciation and amortization of 2.2%, $36,819 a year. A 1-point change in job cost moves Archadeck's average margin by $16,736, which is 45% of that profit.

Job costing

Job costing records each sale and each cost against the job it belongs to. Materials are coded to the job when bought. Crew hours are coded from timesheets. Subcontractor bills and permits are coded when they arrive. The job report then shows estimate against actual for each line.

Worked example: one painting job

A painting job is sold for $12,000 with an estimate of $3,000 of paint and $4,200 of labor. Actual costs come in at $3,300 of paint and $5,100 of labor. The job's margin falls from the estimated $4,800 to $3,600. The job report shows the $900 labor overrun as the larger part of the $1,200 gap.

Percentage of completion and work in progress

On jobs that run over more than one month, percentage of completion records sales as the work is done. It is costs to date divided by total estimated costs. The work-in-progress schedule sets each job's earned sales against what has been billed, so over-billing and under-billing show each month.

Worked example: a remodel at 40%

A remodel is sold for $180,000 with $120,000 of estimated cost. By month end, $48,000 of cost is in, so the job is 40% complete and has earned $72,000. If the customer has been billed $90,000, the job is over-billed by $18,000. That $18,000 is money the business holds for work still to do.

Retainage and change orders

Retainage is the share of each bill a customer holds back until the job is finished, often 5% to 10% on commercial work. It is money owed to the contractor and recorded separately from other receivables. A change order adds to or removes work from a contract, and the books add it to the job's contract value and estimate on the date it is signed.

Worked example: retainage on a commercial job

A $250,000 commercial job with 10% retainage pays $225,000 as the work is billed and holds back $25,000 until the job closes. The books show $25,000 of retainage receivable. A cash forecast places that $25,000 at the closing date, after the crew and material costs have been paid.

Field and trade service businesses

Plumbing, electrical and heating businesses sell short service calls and longer installs. Service calls are costed by technician hours and parts. Installs are job-costed like a remodel. See field services finance resources.

Worked example: CertaPro Painters

CertaPro Painters reports average sales of $2,102,015 and a median of $1,294,333 across 291 franchisees. Cost of goods runs 54.1%, which is $1,137,190 at the average. CertaPro reports EBITDA plus owner’s associate compensation of 9.3%, $195,487 at the average.

Run a contracting or trade business?

Send your open jobs and your last 12 months of statements, and Averan will show what a work-in-progress schedule would say about them.

Talk to Averan

Questions we get asked

What is job costing?

Job costing records every sale and every cost against the job it belongs to: materials, crew hours, subcontractors and permits. Each job then has its own margin, so an owner sees which jobs earned money and which did not.

What is a work-in-progress schedule?

A work-in-progress schedule lists every open job with its contract value, costs to date, estimated cost to finish, percentage complete, and amount billed. It shows whether each job is billed ahead of or behind the work done.